From January 18 to 19th in 2000
We did the completion of the framing with the carpenter and our friends. Floor area of our principal residence is about 127 square yards, and the total area of 1st floor and 2nd floor is about 241 square yards. Also the carpenter uses many thick timbers and assembled firmly, because there are many typhoons in this area. By reason of those the completion of the framing took 2 days with a many number of persons. January 18 did work with 20 people and the next day did work with 8 people.

From January 20 to 31st in 2000
The carpenter attached the rafters, gables, roofing, roof crosspiece etc.

(February 2, 2000)