Table of the Present progress
1998 |
From Feb. | Felled of trees and prepared the soil of housing lot. |
1999 |
February | Decided the position that constructs residence. |
March | Made the floor of the hydro power plant and base of the reservoir by using concrete. Plumbed the water pipe and drainpipe of the water mill. |
April | Almost completed the reservoir. From the foundation to completion of the framing of the hydro power plant. |
May | Established the water power generator. |
From June | Plumbed the waterworks and drainage of the residence. The cut of the material. |
October | Adjusted the water power generator. Made the floor of the residence and base of the fermentation tank by using concrete. |
November | Made the model frame of the fermentation tank and poured concrete there. Made the model frame of the foundation of the residence and ejection tank. |
December | Poured concrete into the model frame of the ejection tank. Made the foundation of the residence by using concrete and laid the foundations of timber. |
2000 |
January | The completion of the framing of our residence. Attached the rafters, gables, roofing, etc. |
February | Attached the chimney, joists, diagonal beams, sashes of several places, etc. |
March | Shingled the roof. |
April | Shingled the roof. Attached sashes and eaveses of sashes. Boarded the exterior wall. |
May | Boarded the exterior wall. Boarded the floor. |
June | Electric wiring. Finished shingling the roof. Boarded the floor. Boarded the interior wall. |
July | Electric wiring. Boarded the interior wall. |
August | Lumbered the big tree of TUGA (for the stairs, edge of the hearth). Boarded the interior wall. |
September | Boarded the interior wall. Made the washstand, storage of bedclothes, shelf of the entrance. Set the balcony and veranda. Ordered fittings. |
October | Covered stainless steel on the edge of the eaves. Ordered the gutter. |
November | Fit up rooms fittings. Attached the gutter. Finished the veranda and balcony. Removed the log of the scaffold. |