Table of the Present progress

1998
From Feb. Felled of trees and prepared the soil of housing lot.
1999
February Decided the position that constructs residence.
March Made the floor of the hydro power plant and base of the reservoir by using concrete. Plumbed the water pipe and drainpipe of the water mill.
April Almost completed the reservoir. From the foundation to completion of the framing of the hydro power plant.
May Established the water power generator.
From June Plumbed the waterworks and drainage of the residence. The cut of the material.
October Adjusted the water power generator. Made the floor of the residence and base of the fermentation tank by using concrete.
November Made the model frame of the fermentation tank and poured concrete there. Made the model frame of the foundation of the residence and ejection tank.
December Poured concrete into the model frame of the ejection tank. Made the foundation of the residence by using concrete and laid the foundations of timber.
2000
January The completion of the framing of our residence. Attached the rafters, gables, roofing, etc.
February Attached the chimney, joists, diagonal beams, sashes of several places, etc.
March Shingled the roof.
April Shingled the roof. Attached sashes and eaveses of sashes. Boarded the exterior wall.
May Boarded the exterior wall. Boarded the floor.
June Electric wiring. Finished shingling the roof. Boarded the floor. Boarded the interior wall.
July Electric wiring. Boarded the interior wall.
August Lumbered the big tree of TUGA (for the stairs, edge of the hearth). Boarded the interior wall.
September Boarded the interior wall. Made the washstand, storage of bedclothes, shelf of the entrance. Set the balcony and veranda. Ordered fittings.
October Covered stainless steel on the edge of the eaves. Ordered the gutter.
November Fit up rooms fittings. Attached the gutter. Finished the veranda and balcony. Removed the log of the scaffold.