Our principal residence

(August 6, 2000)


(August 6, 2000)
Until July 19, 2000
We almost finished electric wiring. We are using the inverters (transformation from DC12V to AC100V of imitation sine wave) of 10 amperes at present. Therefore we are using only one breakers of 10 amperes. However, we divided wiring into 5 circuits as follows, because there is the possibility that increases an electric current in the future.


[Circuit 1] 2 places of lighting and 3 places of wall outlet (dining room), 1 place of lighting (lavatory), 1 place of lighting (kitchen), 1 place of lighting (entrance), 1 place of lighting and 1 place of wall outlet (exterior)
[Circuit 2] 1 place of lighting and 2 places of wall outlet (washroom), 1 place of lighting (bathroom), 1 place of wall outlet (exterior)
[Circuit 3] 1 place of lighting and 1 place of wall outlet (room of the 1st floor), 1 place of wall outlet (refrigerator), 1 place of lighting (sink), 1 place of lighting (ventilating fan), 1 place of lighting (stairs), 1 place of wall outlet (exterior)
[Circuit 4] 1 place of lighting and 2 places of wall outlet (room on the east side of the 2nd floor)
[Circuit 5] 5 places of lighting and 6 places of wall outlet (the 2nd floor other than the room on the east side)

From July 1, 2000
In succession the carpenter boarded the interior wall.


Mid-July, 2000
We plumbed the waterworks of indoor and set the washbowl and toilet bowl in the lavatory. We attached the range hood in the kitchen and set the sink and gas unit.
@
(August 6, 2000)