Reservoir

(April 20, 1999)
Early April, 1999
The carpenter made the model frame.

April 9, 1999
We poured concrete into the model frame with the carpenter.

April 20, 1999
The carpenter removed the model frame. We completed all the plumbing from the reservoir to water mill. It from the right of the photograph in the order of water supply to the reservoir, draw out mud of the reservoir, water supply to the water mill, waterworks to the house and hydro power plant, waterworks for the sprinkling to a farm and overflow.
Hydro power plant

(April 28, 1999)
Early April, 1999
The carpenter made the model frame of foundation.

April 9, 1999
We poured concrete into the model frame of foundation with the carpenter.

April 12, 1999
The carpenter removed the model frame of foundation.

April 27, 1999
We did the completion of the framing with the carpenter and our friends.