Reservoir

(March 29, 1999)
March 26, 1999
Carpenter made the foundation of the reservoir with concrete. We save the overflow of the water purification plant in the reservoir. We filter the water and use in the water mill and residence. The water that is flowing the drain of the right in the photograph is the overflow of the water purification plant.
Hydro power plant

(March 29, 1999)
March 26, 1999
Carpenter made the floor of the hydro power plant with concrete. We plumbed the water pipe and drainpipe of the water mill there beforehand.

The distance from the reservoir to water mill is about 219 yards, the head is about 102 feet. We plumb it with the vinyl pipe of the diameter of about 3 inches. We plumbed it about 55 yards at this time.